title: Period Floor Tiles
|
||||
location: Chelsea, London
|
||||
date: '2020-10-01'
|
||||
features: [Under floor heating]
|
||||
price: £5,600
|
||||
duration: 2 weeks
|
||||
image: 0
|
||||
images: 1
|
||||
---
|
||||
|
||||
Existing floor consisted of dated tiles, client wanted to replace them and install under floor heating at the same time.
|
||||
|
||||
Floor and adhesive was removed and disposed.
|
||||
|
||||
Electric under floor heating system was installed and levelling compound applied.
|
||||
|
||||
54 square meters new tiles were laid, grouted and sealed.
|
||||
|
||||
Total price for labour and materials: £5,600.
|
||||